Heat network data reporting: quarterly and annual returns

Once a network is registered, Ofgem collects data from it every quarter and every year. These are the windows, the due dates and what goes in.

Last checked against Ofgem’s guidance on . General information, not legal advice.

01The duty

Regular data reporting is a condition of authorisation, condition A09. It applies to registered operators and suppliers, and the returns are made through the same digital service as registration.

Ofgem sends a request for information that sets out what to report and when. Do not submit regular data until Ofgem asks for it, and follow the latest request for each submission.

02Quarterly windows and due dates

Ofgem’s quarters run from April to March. Quarterly data is due by the last day of the month after the quarter ends. An extension to the end of the following month can be requested if you have a problem.

  1. Quarter 1 April to June Return due31 July
  2. Quarter 2 July to September Return due31 October
  3. Quarter 3 October to December Return due31 January
  4. Quarter 4 January to March Return due30 April Annual return due the same day

The deadline and every return due in the next 12 months, with a reminder two weeks before each.

03The annual return and financial resilience

Annual data is due by 30 April. Financial resilience figures follow your own accounts: they go in the quarter the accounts are signed off, and no later than 10 months after your financial year end.

Unless Ofgem says otherwise, a figure is the value on the last calendar day of the reporting period.

04Backdating

A network that registers later still owes data recorded from April 2026 up to its first submission. Ofgem has said it will accept whatever is available for April to June 2026.

05What Ofgem is looking at

The data is grouped around five themes:

  • Debt
  • Fair pricing
  • Financial resilience
  • Quality of service, including complaints
  • Vulnerability

Separately from the returns, tell Ofgem about material changes as they happen, such as a sale of the building, a new heat source or adding a connected building.

06Having it done for you

For a small block the figures are not complicated, but the windows come round four times a year for as long as you run the network. The blockpath subscription files every quarterly and annual return for a fixed monthly fee per block, with your approval before each one goes in. How it works shows the year.